title Implementation Roadmap
description Detailed task breakdown with dependencies, estimates, and acceptance criteria

Overview

This roadmap breaks down the 90-day MVP into specific, actionable tasks with time estimates, dependencies, and acceptance criteria. Use this as the primary reference for sprint planning.

Total Duration: 12 weeks (6 x 2-week sprints) Team Size: 4.5 FTE Total Estimated Hours: 1,800 hours


Week-by-Week Breakdown

Week 1: Infrastructure Foundation

Sprint: Sprint 1 (Week 1-2) Team Focus: Platform Engineer (100%), DevOps (100%)

Tasks

Task ID Task Owner Hours Dependencies Status
INF-001 Provision cloud resources (VPC, subnets, security groups) DevOps 8 - ⏳ Pending
INF-002 Deploy ClickHouse cluster (3 nodes, RF=2) Platform 16 INF-001 ⏳ Pending
INF-003 Deploy PostGIS (RDS/CloudSQL) Platform 8 INF-001 ⏳ Pending
INF-004 Deploy Valkey cache (2 nodes) Platform 4 INF-001 ⏳ Pending
INF-005 Set up Kafka cluster (3 brokers) Platform 12 INF-001 ⏳ Pending
INF-006 Deploy Keycloak (auth server) DevOps 8 INF-001 ⏳ Pending
INF-007 Set up GitHub Actions CI/CD DevOps 8 - ⏳ Pending
INF-008 Configure Prometheus + Jaeger DevOps 8 INF-001 ⏳ Pending

Week 1 Total: 72 hours

Acceptance Criteria

  • ✅ ClickHouse accessible and responding to queries
  • ✅ PostGIS accepting connections with PostGIS extension enabled
  • ✅ Valkey responding to PING command
  • ✅ Kafka brokers forming cluster (3/3 healthy)
  • ✅ Keycloak admin console accessible
  • ✅ CI/CD pipeline running (at least dummy job)
  • ✅ Prometheus scraping all services

Week 2: API Scaffolding

Sprint: Sprint 1 (Week 1-2) Team Focus: Backend Engineer (100%), Platform Engineer (50%)

Tasks

Task ID Task Owner Hours Dependencies Status
API-001 Create FastAPI project structure Backend 4 - ⏳ Pending
API-002 Implement OAuth 2.0 client credentials flow Backend 12 INF-006 ⏳ Pending
API-003 Create OpenAPI spec (signals, sites, alerts) Backend 16 API-001 ⏳ Pending
API-004 Implement ClickHouse client wrapper Backend 8 INF-002 ⏳ Pending
API-005 Implement PostGIS client wrapper Backend 8 INF-003 ⏳ Pending
API-006 Implement Valkey cache layer Backend 8 INF-004 ⏳ Pending
API-007 Create database migration scripts Platform 12 INF-002, INF-003 ⏳ Pending
API-008 Write unit tests for auth flow Backend 8 API-002 ⏳ Pending

Week 2 Total: 76 hours

Acceptance Criteria

  • ✅ FastAPI server starts and serves /docs (Swagger UI)
  • ✅ OAuth token can be obtained with client credentials
  • ✅ OpenAPI spec validates (no errors)
  • ✅ ClickHouse client executes SELECT 1 successfully
  • ✅ PostGIS client executes SELECT PostGIS_version()
  • ✅ Valkey cache SET/GET operations work
  • ✅ Migrations create all tables without errors
  • ✅ Unit tests pass (>80% coverage)

Week 3: Core API Endpoints

Sprint: Sprint 2 (Week 3-4) Team Focus: Backend Engineer (100%)

Tasks

Task ID Task Owner Hours Dependencies Status
API-009 Implement POST /v1/sites (create site) Backend 8 API-005 ⏳ Pending
API-010 Implement GET /v1/sites (list sites) Backend 4 API-009 ⏳ Pending
API-011 Implement GET /v1/sites/{id} Backend 4 API-009 ⏳ Pending
API-012 Implement PATCH /v1/sites/{id} Backend 4 API-009 ⏳ Pending
API-013 Implement DELETE /v1/sites/{id} Backend 4 API-009 ⏳ Pending
API-014 Add input validation (Pydantic models) Backend 8 API-009 ⏳ Pending
API-015 Add pagination to list endpoints Backend 8 API-010 ⏳ Pending
API-016 Write integration tests for sites API Backend 12 API-013 ⏳ Pending

Week 3 Total: 52 hours

Acceptance Criteria

  • ✅ Can create site with valid GeoJSON polygon
  • ✅ Can list sites (supports pagination)
  • ✅ Can get site by ID
  • ✅ Can update site name/metadata
  • ✅ Can delete site
  • ✅ Input validation rejects invalid data (400 error)
  • ✅ Integration tests pass

Week 4: Signals Query API

Sprint: Sprint 2 (Week 3-4) Team Focus: Backend Engineer (100%), Platform Engineer (25%)

Tasks

Task ID Task Owner Hours Dependencies Status
API-017 Implement POST /v1/signals:query (basic) Backend 16 API-004 ⏳ Pending
API-018 Add rollup support (5m, 15m, 1h, 1d) Backend 12 API-017 ⏳ Pending
API-019 Add Valkey caching (5-min TTL) Backend 8 API-006, API-017 ⏳ Pending
API-020 Add provenance field to response Backend 4 API-017 ⏳ Pending
API-021 Optimize query performance (indexes) Platform 8 API-017 ⏳ Pending
API-022 Write integration tests for signals query Backend 12 API-020 ⏳ Pending
API-023 Load test with k6 (1000 req/sec target) DevOps 8 API-019 ⏳ Pending

Week 4 Total: 68 hours

Acceptance Criteria

  • ✅ Can query signals for site_id + metric + time range
  • ✅ Rollup returns correct aggregated values
  • ✅ Cache hit rate >90% for repeated queries
  • ✅ Provenance includes sources, model_version
  • ✅ p95 latency <2.5s (cold), <800ms (cached)
  • ✅ Integration tests pass
  • ✅ Load test achieves 1000 req/sec

Week 5: Edge Device Setup

Sprint: Sprint 3 (Week 5-6) Team Focus: ML Engineer (100%), Platform Engineer (25%)

Tasks

Task ID Task Owner Hours Dependencies Status
EDGE-001 Flash Jetson Orin with Ubuntu 22.04 + JetPack ML 4 - ⏳ Pending
EDGE-002 Install PaddlePaddle + PP-YOLOE model ML 8 EDGE-001 ⏳ Pending
EDGE-003 Implement vehicle detection script ML 12 EDGE-002 ⏳ Pending
EDGE-004 Integrate ByteTrack for tracking ML 12 EDGE-003 ⏳ Pending
EDGE-005 Implement DeepPrivacy2 redaction ML 12 EDGE-001 ⏳ Pending
EDGE-006 Test on sample video (accuracy check) ML 8 EDGE-004, EDGE-005 ⏳ Pending
EDGE-007 Optimize for real-time (>20 FPS) ML 16 EDGE-006 ⏳ Pending
EDGE-008 Create deployment image (Docker/Balena) Platform 8 EDGE-007 ⏳ Pending

Week 5 Total: 80 hours

Acceptance Criteria

  • ✅ PP-YOLOE detects vehicles in video
  • ✅ ByteTrack assigns consistent IDs across frames
  • ✅ DeepPrivacy2 blurs faces/plates (>95% accuracy)
  • ✅ Inference runs at >20 FPS on Jetson
  • ✅ Deployment image can be flashed to new Jetsons

Week 6: MQTT → Kafka Pipeline

Sprint: Sprint 3 (Week 5-6) Team Focus: ML Engineer (50%), Platform Engineer (100%)

Tasks

Task ID Task Owner Hours Dependencies Status
STREAM-001 Deploy Eclipse Mosquitto MQTT broker Platform 4 INF-001 ⏳ Pending
STREAM-002 Implement MQTT publisher on Jetson ML 12 EDGE-007, STREAM-001 ⏳ Pending
STREAM-003 Create MQTT → Kafka bridge Platform 16 STREAM-001, INF-005 ⏳ Pending
STREAM-004 Test end-to-end latency (<10s) Platform 8 STREAM-003 ⏳ Pending
STREAM-005 Add message schema validation Platform 8 STREAM-003 ⏳ Pending
STREAM-006 Monitor Kafka lag (Prometheus) DevOps 4 STREAM-003 ⏳ Pending

Week 6 Total: 52 hours

Acceptance Criteria

  • ✅ Jetson publishes detections to MQTT
  • ✅ MQTT messages appear in Kafka topic
  • ✅ End-to-end latency <10 seconds
  • ✅ Message schema validates (Avro/Protobuf)
  • ✅ Kafka lag is monitored and <5 seconds

Week 7: Stream Processing (Flink)

Sprint: Sprint 4 (Week 7-8) Team Focus: Platform Engineer (100%)

Tasks

Task ID Task Owner Hours Dependencies Status
STREAM-007 Deploy Flink cluster (2 task managers) Platform 8 INF-001 ⏳ Pending
STREAM-008 Implement Flink job for occupancy count Platform 16 STREAM-003, STREAM-007 ⏳ Pending
STREAM-009 Implement 5-min window aggregation Platform 12 STREAM-008 ⏳ Pending
STREAM-010 Implement 15-min, 1h, 1d rollups Platform 16 STREAM-009 ⏳ Pending
STREAM-011 Add quality_score computation Platform 8 STREAM-008 ⏳ Pending
STREAM-012 Insert into ClickHouse Platform 12 INF-002, STREAM-010 ⏳ Pending

Week 7 Total: 72 hours

Acceptance Criteria

  • ✅ Flink job consumes from Kafka topic
  • ✅ Occupancy metric computed correctly
  • ✅ 5m, 15m, 1h, 1d rollups created
  • ✅ Quality score between 0-1
  • ✅ Data appears in ClickHouse within 10 seconds

Week 8: Edge Deployment

Sprint: Sprint 4 (Week 7-8) Team Focus: ML Engineer (50%), DevOps (50%)

Tasks

Task ID Task Owner Hours Dependencies Status
EDGE-009 Order 10 Jetson Orin Nano devices PM 2 - ⏳ Pending
EDGE-010 Order 10 IP cameras PM 2 - ⏳ Pending
EDGE-011 Flash 10 Jetson devices ML 8 EDGE-008, EDGE-009 ⏳ Pending
EDGE-012 Install cameras at 10 pilot sites DevOps 40 EDGE-010 ⏳ Pending
EDGE-013 Configure network (WiFi/LTE) DevOps 16 EDGE-012 ⏳ Pending
EDGE-014 Validate data ingestion (all 10 sites) Platform 8 EDGE-013, STREAM-012 ⏳ Pending

Week 8 Total: 76 hours

Acceptance Criteria

  • ✅ 10 Jetson devices flashed and running
  • ✅ 10 cameras installed and streaming
  • ✅ All 10 sites sending data to ClickHouse
  • ✅ Data quality >0.7 average
  • ✅ Uptime >95% over 48 hours

Week 9: Satellite Imagery

Sprint: Sprint 5 (Week 9-10) Team Focus: ML Engineer (100%)

Tasks

Task ID Task Owner Hours Dependencies Status
SAT-001 Sign up for Sentinel-2 API access ML 2 - ⏳ Pending
SAT-002 Download 100 parcel tiles ML 8 SAT-001 ⏳ Pending
SAT-003 Implement roof segmentation (SAM/U-Net) ML 24 SAT-002 ⏳ Pending
SAT-004 Compute roof area, slope, aspect ML 12 SAT-003 ⏳ Pending
SAT-005 Validate geometry (error <5%) ML 8 SAT-004 ⏳ Pending
SAT-006 Store results in PostGIS ML 8 INF-003, SAT-005 ⏳ Pending

Week 9 Total: 62 hours

Acceptance Criteria

  • ✅ 100 parcel tiles downloaded
  • ✅ Roof segmentation masks generated
  • ✅ Roof area error <5% vs. ground truth (n≥50)
  • ✅ Results stored in PostGIS model_inferences table

Week 10: Solar Analysis

Sprint: Sprint 5 (Week 9-10) Team Focus: ML Engineer (50%), Platform Engineer (50%)

Tasks

Task ID Task Owner Hours Dependencies Status
SAT-007 Sign up for Earth Engine commercial API PM 2 - ⏳ Pending
SAT-008 Implement insolation query (NASA/NREL) ML 12 SAT-007 ⏳ Pending
SAT-009 Compute shade_index (NDVI) ML 8 SAT-007 ⏳ Pending
SAT-010 Calculate solar_score (combined metric) ML 8 SAT-008, SAT-009 ⏳ Pending
SAT-011 Estimate payback period ML 8 SAT-010 ⏳ Pending
SAT-012 Store in ClickHouse Platform 4 SAT-011, INF-002 ⏳ Pending
SAT-013 Validate solar_score (±15% payback) ML 8 SAT-012 ⏳ Pending

Week 10 Total: 50 hours

Acceptance Criteria

  • ✅ Insolation data retrieved for 100 parcels
  • ✅ Shade index computed
  • ✅ Solar score between 0-1
  • ✅ Payback estimate within ±15% of baseline
  • ✅ Results in ClickHouse

Week 11: Map Interface (Core)

Sprint: Sprint 6 (Week 11-12) Team Focus: Frontend Engineer (100%)

Tasks

Task ID Task Owner Hours Dependencies Status
UI-001 Create React app with Vite + TypeScript Frontend 4 - ⏳ Pending
UI-002 Integrate MapLibre GL JS Frontend 8 UI-001 ⏳ Pending
UI-003 Add Protomaps tiles Frontend 4 UI-002 ⏳ Pending
UI-004 Implement parcel layer (GeoJSON) Frontend 12 UI-002, API-017 ⏳ Pending
UI-005 Add color coding by roof_condition Frontend 8 UI-004 ⏳ Pending
UI-006 Implement click handler (parcel selection) Frontend 8 UI-004 ⏳ Pending
UI-007 Create property details modal Frontend 16 UI-006 ⏳ Pending
UI-008 Add tabs (Overview, RoofIQ, SolarFit, Demographics) Frontend 12 UI-007 ⏳ Pending

Week 11 Total: 72 hours

Acceptance Criteria

  • ✅ Map loads with Protomaps tiles
  • ✅ Parcels displayed on map
  • ✅ Parcels colored by roof_condition
  • ✅ Clicking parcel opens modal
  • ✅ Modal shows property details
  • ✅ All tabs functional

Week 12: Advanced Features

Sprint: Sprint 6 (Week 11-12) Team Focus: Frontend Engineer (100%)

Tasks

Task ID Task Owner Hours Dependencies Status
UI-009 Integrate Mapbox GL Draw (territory drawing) Frontend 12 UI-002 ⏳ Pending
UI-010 Implement save territory (POST /v1/territories) Frontend 8 UI-009, API-017 ⏳ Pending
UI-011 Create advanced search (Cmd+K) with shadcn/ui Frontend 16 UI-001 ⏳ Pending
UI-012 Add filter panel (left sidebar) Frontend 12 UI-011 ⏳ Pending
UI-013 Integrate Census API (demographics overlay) Frontend 12 UI-002 ⏳ Pending
UI-014 Add heat map layer (Deck.gl) Frontend 12 UI-002 ⏳ Pending
UI-015 Write E2E tests (Playwright) Frontend 8 UI-014 ⏳ Pending

Week 12 Total: 80 hours

Acceptance Criteria

  • ✅ User can draw and save territories
  • ✅ Advanced search (Cmd+K) functional
  • ✅ Filter panel updates map
  • ✅ Demographics overlay displays
  • ✅ Heat map layer works
  • ✅ E2E tests pass

Dependencies Graph

graph TD
    INF[Infrastructure Week 1] --> API[API Scaffolding Week 2]
    API --> CORE[Core Endpoints Week 3-4]
    CORE --> SIGNALS[Signals Query Week 4]

    INF --> EDGE[Edge Setup Week 5]
    EDGE --> MQTT[MQTT Pipeline Week 6]
    MQTT --> FLINK[Flink Processing Week 7]
    FLINK --> DEPLOY[Edge Deployment Week 8]

    SIGNALS --> SAT[Satellite Week 9]
    SAT --> SOLAR[Solar Analysis Week 10]

    SOLAR --> UI[Map Interface Week 11]
    UI --> ADVANCED[Advanced Features Week 12]
Loading

Resource Allocation

Weekly Team Hours

Week Platform Eng ML Eng Backend Eng Frontend Eng DevOps PM Total
1 40 0 0 0 40 4 84
2 20 0 40 0 8 4 72
3 0 0 40 0 8 4 52
4 10 0 40 0 8 4 62
5 10 40 0 0 8 4 62
6 40 20 0 0 4 4 68
7 40 0 0 0 8 4 52
8 8 20 0 0 20 4 52
9 0 40 0 0 8 4 52
10 20 20 0 0 8 4 52
11 0 0 0 40 8 4 52
12 0 0 0 40 8 4 52
Total 188 140 120 80 136 48 712

Tracking & Reporting

Daily Standup Format

Time: 9:00 AM, 15 minutes Attendees: All engineers

Questions:

  1. What did you complete yesterday?
  2. What will you work on today?
  3. Any blockers?

Output: Update task status in project management tool (Jira/Linear)

Sprint Review

Time: Last day of sprint, 2 hours Attendees: Team + stakeholders

Agenda:

  1. Demo working features (30 min)
  2. Review sprint goals vs. actual (15 min)
  3. Metrics review (15 min)
    • Velocity (story points completed)
    • Quality (test coverage, bug count)
    • Performance (API latency, uptime)
  4. Stakeholder Q&A (30 min)
  5. Next sprint preview (15 min)

Weekly Metrics Report

Sent: Friday 5 PM Recipients: Team + stakeholders

Metrics:

  • Velocity: Story points completed vs. planned
  • Quality: Test coverage, critical bugs
  • Performance: API p95 latency, uptime
  • Risks: Blockers, dependencies delayed

Next Steps

Review the overall development methodology Understand the system architecture Review the technology stack Begin with infrastructure setup